Rolling Road Widening Project Update VDOT’s amended schedule follows. Phase I expands the Rolling Road northbound turn lanes at the Old Keene Mill Rd intersection. Phase II widens the road to two through lanes in each direction plus pedestrian/bicycle facilities.
Phase I Begin Right of Way Acquisition – delayed to July 2019
Phase I Begin Utility Relocation - Spring 2019 – delayed, but no update on start
Phase I Construction – delayed to Winter 2020/2021
Phase II Begin Right of Way Acquisition – Fall/Winter 2019
Phase II Begin Utility Relocation - Winter 2020
Phase II Construction – delayed to Spring 2023 start; 2 year project.